# Mombasa Cement Seeks EPRA Approval for 12MW Coal Plant

> Mombasa Cement applies to Kenya's EPRA for a 12MW coal-fired plant and 2.217MWp solar expansion in Vipingo, according to AllAfrica: Kenya reporting.

- By: Editorial Team, Somali Construction Review (https://somaliconstructionreview.com/about)
- Published: 27 November 2026
- Format: News story (reported from one named public source)
- Publication: Somali Construction Review (https://somaliconstructionreview.com)
- Subject: Infrastructure and Services
- Tags: cement, utilities
- Web version: https://somaliconstructionreview.com/blog/mombasa-cement-12mw-coal-solar-approval

## Key points

- Mombasa Cement has applied to Kenya's EPRA to build a 12-megawatt coal-fired power plant in Vipingo, Kilifi County, according to AllAfrica: Kenya.
- The company is also seeking approval to add 2.217 MWp of solar capacity to its existing 9.858 MWp installation, bringing the total to about 12.08 MWp.
- The report does not state project costs, contractors, timelines, or whether EPRA has approved either application.

Mombasa Cement has applied for regulatory approval to build a 12-megawatt coal-fired power plant and expand its solar generation at its Vipingo facility in Kilifi County, according to a report by Capital FM (Nairobi), authored by Phidel Kizito and carried by AllAfrica: Kenya on 27 November 2026.

The proposed coal plant would use a Circulating Fluidized Bed Combustion (CFBC) boiler to generate steam driving a 12MW turbine, with coal as the primary fuel, the report states. The company says the cogeneration plant would supply electricity directly to its factory while improving manufacturing efficiency, according to AllAfrica: Kenya.

Mombasa Cement also seeks approval to add 2.217 megawatt-peak (MWp) of solar capacity to its existing 9.858MWp installation, bringing the total to about 12.08MWp, the report says. The additional solar power would be used exclusively by the company and not supplied to the national grid.

The report notes that the applications come as manufacturers seek ways to manage electricity costs and secure reliable power. It also raises questions about industrial emissions from the proposed coal plant as Kenya pursues a transition to cleaner energy sources, though no specific critic, regulator, or study is named.

Neither the report nor other public records confirm whether the Energy and Petroleum Regulatory Authority (EPRA) has accepted, scheduled, granted, or rejected either application. No project cost, financing source, contractor, construction timeline, or completion date is stated.

## Questions

### What is the proposed capacity of the coal plant?

12 megawatts, using a Circulating Fluidized Bed Combustion (CFBC) boiler and a 12MW turbine, as reported by AllAfrica: Kenya.

### What solar expansion is planned?

Mombasa Cement is seeking approval to add 2.217 MWp to its existing 9.858 MWp installation, for a projected total of about 12.08 MWp, according to AllAfrica: Kenya.

### What is the timeline and current status?

Licence applications have been submitted to EPRA, but no approval, construction start, or completion date is reported.