In brief
- Delay records experience gaps show up as site diaries without dates, causes or a clear link between an event and the days claimed.
- A client can close the gap by requiring daily records, a simple cause code for every lost day and one agreed format from every contractor before work starts.
- Ask the contractor and recent clients what records exist, and read the site diary yourself during the build.
Contents
Delay records experience gaps in Gabiley put projects at risk because the people keeping the site diary may never have kept one that had to survive a claim. Time is lost to rain, material late from the port, power cuts, a wall that has to be opened again. If nobody writes down the date, the cause and the activity that stopped, the client carries the loss and the final account becomes an argument.
How do delay records experience gaps show up in Gabiley?
The first sign is a diary that records activity but not interruption. Pages say the site was working or the crew was on blockwork. Nothing says how many people, which activity stopped, or when it restarted. A second sign is a cause code applied late. A foreman remembers the rain three weeks after the wet spell and writes one line covering several days, which no supervisor can verify against the programme.
A third sign is the missing link between event and effect. A late delivery of cement is recorded as a delivery note, not as days of lost blockwork. Without an activity reference and a revised date, the record cannot support any extension of time.
A thin record may come from inexperience rather than dishonesty. Recording delay is a separate skill from building. Ask the contractor to show a diary from a completed job and read it against that project's programme. If the two cannot be lined up, expect the same risk on your project.
Where does unclear lost time hit the programme?
Unclear causes of lost time hit the critical path first, because that is where a day lost moves the completion date. When the record does not separate delay to a critical activity from delay to a trade with float, every lost hour looks equally serious and the claim becomes guesswork.
It also hits cash. A contractor who cannot show which days were lost cannot support a variation or a claim for added preliminaries, and the dispute can stall later payments. That pressure can push a crew to hurry finishes, which is where defects start.
For the client, the cost is a completion forecast with no date behind it. A project manager can only report what the records show. General practice on commercial projects is a daily record signed by the site supervisor, an activity reference, a cause code and the weather, but confirm the format with the project's engineer and specification before adopting it. Ask the project's engineer and specification to confirm the record requirements, and follow that.
How do you detect the gap before work starts?
Detect it in the tender and the interview, not after mobilisation. Ask each bidder for a sample delay record from a recent job, the programme that goes with it and the name of the person who signs it. Two documents that reconcile show the skill exists.
At interview, walk through one real event: what happened, when it was noticed, who recorded it, how many days were claimed and what the client did. Vague answers point to a gap.
Cover these checks:
- A sample daily record with dates, weather, crew numbers, activities and interruptions.
- One cause code list agreed in writing before mobilisation.
- A named person, with a deputy, responsible for the diary even when the supervisor is away.
- One format for all trades, so records can be read side by side.
Write the record format and the submission interval into the contract, then check that the contract allows the arrangement, asking a quantity surveyor if the wording is unclear.
What to do next
Before signing, ask the contractor for one recent delay record and the programme it belongs to, then read them together. If they do not match, require a daily record format, a cause code list and a named recorder in the contract. Visit the site during the first month and check the diary is being filled in daily, not reconstructed later.
Frequently asked questions
What should a daily site record contain in Gabiley?
Date, weather, crew numbers by trade, activities worked, activity references from the programme, deliveries, interruptions, the cause of each interruption and the signature of the site supervisor. Ask the project's engineer to confirm the exact format for your contract.
Can a client reject a claim with no delay records?
The contract decides what evidence is required. Read the clause on notices and records, and take advice from a quantity surveyor or legal adviser before responding to any claim.
How does a client check a contractor's delay records experience?
Ask for a sample record and programme from a completed job and reconcile the two, then question the contractor about one event in that job: cause, dates, days claimed and the outcome.
Local reporting: this article is written for building work in Gabiley and Somaliland. Ground conditions, prices and rules differ between places; confirm the details for your own site.