Western Bosaso 3.5 MW solar plant

A 3.5 MW solar PV plant in western Bosaso that the African Development Bank's appraisal of November 2025 describes as completed but not yet connected to the network, with connection expected by the beginning of 2026.

  • Completed
  • Sourced, not yet verified

The project in brief

Place
Bosaso, Puntland
Type
Power and energy
Status
Completed: Bosaso's 3.5 MW solar plant built but unconnected, with connection expected in early 2026
Value
Not published
Start
Not published
Expected completion
Not published
Completed
Not published
Progress
Not published
Last checked
21 September 2026

Organisations named

No source names a contractor, consultant, funder or other organisation on this project.

What the sources report

  1. November 2025

    Bosaso's 3.5 MW solar plant built but unconnected, with connection expected in early 2026

    The AfDB appraisal report states that a 3.5 MW solar PV plant in western Bosaso is completed but not yet connected to the network, with connection expected by the beginning of 2026.

    African Development Bank, funder appraisal report. Source · Our report

Related coverage

Sources and their limits

How this record was put together

One fact from the Bosaso grid appraisal, recorded apart from the grid project because it is a separate plant.

Figures are as the sources state them, with the dates they give. A correction or a newer source: tell the desk.