A proposed road corridor from Garacad port inland. Horn Review described it in March 2025 as 270 km, estimated at USD 216 million, linking the port to Galkayo and Galdogob towards the Ethiopian border, with security, funding and political cooperation still to be settled. In July 2025 Puntland's president announced a new highway from Garacad port to the Tuuri-Dibi customs checkpoint in Galdogob district, WardheerNews reported. No funder commitment, design or start date is documented.
- Planned, as of 17 March 2025
- Verified by the desk
- Grouping under review
The project in brief
- Place
- Galkayo, Puntland
- Type
- Road
- Status
- Planned, as of 17 March 2025: Garacad corridor: 270 km and USD 216 million from the port to Galkayo and Galdogob
- Value
- USD 216 million, estimate for the proposal, as reported
- Start
- Not published
- Expected completion
- Not published
- Completed
- Not published
- Progress
- Not published
- Last checked
- 14 October 2026, verified by the desk on 14 October 2026
Organisations named
No source names a contractor, consultant, funder or other organisation on this project.
What the sources report
- 4 July 2025
A new highway from Garacad port to the Tuuri-Dibi customs post in Galdogob
The president announced a new highway linking Garacad port to the Tuuri-Dibi customs checkpoint in Galdogob district, intended to move goods from the port to Ethiopia, according to the report.
- 17 March 2025
Garacad corridor: 270 km and USD 216 million from the port to Galkayo and Galdogob
Horn Review described a proposed 270 km Garacad corridor estimated to cost USD 216 million, linking Garacad port to Galkayo and Galdogob and extending toward the Ethiopian border.
- 17 March 2025
Security, funding and political cooperation: the corridor's open questions
Horn Review wrote that security, funding and political cooperation will need to be addressed for the Garacad corridor to be completed, while describing the port as driven by local business leaders.
Related coverage
Sources and their limits
- Horn Review: Garacad corridor USD 216 million road
Commentary / analysis, 17 March 2025. Checked 21 September 2026.
What it does not establish: Analysis piece; the USD 216 million and 270 km are the proposal as reported; no funder commitment, design status or start date is documented.
- WardheerNews: Garacad port handover to a UAE company
Attributed reporting of presidential statements, 4 July 2025. Checked 21 September 2026.
What it does not establish: The UAE company is unnamed; no agreement text, terms or road design was published; the source notes transparency concerns.
How this record was put together
PLAN-034 and PLAN-035 share one source. PLAN-037 names a highway from Garacad port to Galdogob district, which matches the corridor's route but not its description; grouped as the same corridor pending review.