Projects · Water supply · Hargeisa

Hargeisa water expansion: boreholes and reservoirs

The Hargeisa Water Agency's expansion of the city's supply. The agency reported its fourth borehole in May 2025, 212 m deep, and the fifth of six planned second-phase boreholes in August 2025, 230 m deep in Darasalam district and producing 60 m³ an hour, with reservoir works nearing completion. The next step it named is connecting the new boreholes to the Geedeeble reservoirs. The figures are the agency's own.

  • Under construction, as of 21 August 2025
  • Verified by the desk

The project in brief

Place
Hargeisa, Somaliland
Type
Water supply
Status
Under construction, as of 21 August 2025: Fifth of six boreholes: 230 m deep and 60 m3 an hour at Darasalam
Value
Not published
Start
Not published
Expected completion
Not published
Completed
Not published
Progress
Not published
Last checked
29 September 2026, verified by the desk on 29 September 2026

Organisations named

What the sources report

  1. 21 August 2025

    Fifth of six boreholes: 230 m deep and 60 m3 an hour at Darasalam

    The Hargeisa Water Agency reported the inauguration of the fifth of six boreholes planned for the second phase of the expansion, in Darasalam district, drilled to 230 metres with water first reached at 45 metres and a production rate of 60 cubic metres per hour.

    Hargeisa Water Agency, agency report. Source · Our report

  2. 21 August 2025

    Next step for Hargeisa water: connecting the new boreholes to the Geed Deeble reservoirs

    The agency said that with the fifth borehole complete it is nearing the end of the drilling phase, and that the next steps involve connecting the new boreholes and integrating them into the existing Geedeeble reservoirs.

    Hargeisa Water Agency, agency report. Source · Our report

  3. 4 June 2025

    Hargeisa's fourth borehole: 212 m deep, water met at 22 m

    The Hargeisa Water Agency reported that the fourth borehole of the Hargeisa Water Expansion project, inaugurated on 29 May 2025, reaches a depth of 212 metres with water identified at 22 metres below the surface.

    Hargeisa Water Agency, agency report. Source · Our report

  4. 4 June 2025

    Reservoir works in Hargeisa nearing completion, the water agency reports

    The agency's general manager told the vice president that significant advances had been made on reservoir development within the city, with the project nearing completion and preparations for comprehensive testing under way.

    Hargeisa Water Agency, agency report. Source · Our report

Related coverage

Sources and their limits

How this record was put together

Two agency reports about the same expansion project.

Figures are as the sources state them, with the dates they give. A correction or a newer source: tell the desk.