In brief
- A completion date is a claim about labour, plant and materials, so a bid review should test it against those three things rather than accept the calendar.
- Ask for the method statement, the crew list and the equipment list before you score the programme, because a fast date with no matched resources is a promise the site cannot keep.
- Write the programme into the contract as a document you can request updates against, so schedule slippage shows up early enough to act on.
Contents
Bid program reviews in Burao often pass a completion date that no crew on the ground can meet. The programme looks tidy on paper, the price is low, and the dates are tight. The gap sits in the review itself: nobody checks whether the bidder has the skills, the plant and the material supply to hold that date. When the work starts, the schedule slips, the client pays twice for rework, and the contractor blames the market.
What does a bid program review actually check in Burao?
A bid program review checks whether the dates in the tender match the resources the bidder can actually put on site. That means three checks, done together, not one after the other. First, read the method statement and ask which trade does which task, in what order. Second, ask for the crew list and the CVs or reference sites for the foreman and the key trades. Third, ask for the equipment list with ownership or hire evidence. A date without those three behind it is a wish, not a program.
For a building in Burao, ask the bidder to show how many masons, carpenters and steel fixers will be on site each week, and where they worked before. Ask where the cement, steel and aggregates will come from, and what happens if a delivery is late. Ask the municipal engineer's office what permit or inspection steps sit in the programme, since those dates can shift the whole schedule. Do not accept a bar chart with no resource loading behind it.
Why do unrealistic completion promises survive the review?
Unrealistic completion promises survive because the review scores the document, not the delivery capacity behind it. A bidder who has never run a job of that size can still write a clean programme. If the evaluation panel has no engineer who has built in the region, the panel has no way to test the claim. The skills gap is in the reviewer, not only the bidder.
The second reason is time. A short tender window pushes panels to score price and dates and leave method and resources for later. The third is that the same few contractors bid for many jobs, so a low bid with a fast date wins on paper while the crew is already committed elsewhere. Ask each bidder to state how many active sites they hold and who supervises each one. That answer, written into the bid, is the cheapest test you have. Confirm any regulatory step with the office that issues it, not with the bidder.
How do you close the gap before award?
Close the gap by making the programme a contract document with named people and dated updates. Before award, ask for a one-page resource schedule: crew numbers by trade, plant on site, and material delivery dates. Ask the bidder to name the site agent and the foreman, with a short record of comparable work. Score that schedule alongside price.
After award, require a weekly update against the same schedule, and walk the site to compare the crew on the ground with the crew in the document. A shortfall shows up in days, not months. If the contract allows, make the named key staff and the equipment list part of the agreement, so a swap needs your written agreement. Check what your contract allows before you rely on that clause. For public work, ask the procuring office which documents it will enforce, and copy that wording into your own tender.
What to do next
Take one live tender and ask each bidder for a resource-loaded programme: crew by trade, plant by week, material delivery dates and the named site agent. Score that against price before you award. If the programme and the resources do not match, ask the bidder to revise or explain in writing, and record the answer in the tender file.
Frequently asked questions
Can a low bid still be a good bid in Burao?
A low bid can be workable if the resource schedule behind it holds up: named crew, owned or hired plant, and confirmed material supply. Test those three before you treat the price as real.
Who should sign off the programme dates?
The bidder signs the programme, and the panel or client engineer countersigns after checking the resources. Ask the procuring office which signature it requires for the type of contract you are running.
Local reporting: this article is written for building work in Burao and Somaliland. Ground conditions, prices and rules differ between places; confirm the details for your own site.