In brief
- One foreman cannot supervise two active sites at once, because supervision needs continuous presence in daylight hours.
- Ask for a written site list with foreman names, plot references and current stage, then walk the sites named.
- Check whether the contract ties the named foreman to the plot and sets a replacement procedure.
Contents
A foreman shared across several Garowe jobs cannot hold site supervision. Supervision is a presence task: checking setting out, formwork and cover to reinforcement before concrete goes in. One person cannot stand on two plots at once, so one of the sites runs unsupervised for most of the working day. The fix is to verify foreman capacity in Garowe before the work starts, not after a defect appears.
Why does splitting one foreman across sites fail in Garowe?
Every activity that must be inspected before it is covered needs a person there when it happens. When one foreman covers two jobs, concrete gets poured on the day he is elsewhere. The crew then decides for itself how much cover to leave and how tightly to brace formwork, and those decisions are buried by the pour.
Travel between plots makes this worse. A short hop across town can become a long absence once the route, a materials delivery and a supplier stop are added. A plausible arrangement to suggest is a named foreman present on site for the working day, with a deputy for the hours he is away, and this arrangement should be confirmed against the project's specification or engineer.
Watch for the failure signatures: soaked subgrade left open overnight, honeycombed concrete at the edges, blockwork courses rising faster than the mortar sets, and workers who cannot say who approves an inspection. Each one points to a decision made without a supervisor standing there.
What does the split do to your programme and final account?
Rework costs time before it costs money. A wall built out of plumb is demolished or patched, and the following trades wait. The client feels it as a stalled programme and a thicker defects list at handover.
It also weakens your records. A foreman moving between plots cannot sign daily sheets on both, so the diary develops gaps. When a variation or a delay claim is discussed, nobody can show what was built on which day. Ask what the contract says about daily records, who signs them and whether the contractor must keep a site diary on the plot.
Ask two contractors how they allocate a foreman to a single job, and ask for the name of the person who will hold that role on your plot. The answer is checkable. If the name changes weekly, the allocation is thin, and the client should weigh that in bid evaluation.
How do you verify foreman capacity before signing?
Verify in writing, then on the ground. Ask for a current site list with foreman names, plot references, contract status and the stage each site has reached. Ask for contact details of clients on the sites named, then call one and ask who was on site last week.
Walk a recent completed job with the proposed foreman and ask what he checked before the first pour, what he did when a test failed and which trade he sequenced first. Specific answers show he was there and handled the decision.
Ask the municipal engineer's office which plot records it holds and how to obtain them, and request the contractor's own records for the named sites. Ask the contractor to state in writing how many active sites each foreman holds, what the deputy arrangement is and how a replacement foreman is approved. Then check the contract: a clause tying the named foreman to the plot, with a procedure for any substitution, lets you compare what was promised with what arrives.
What to do next
Ask the contractor bidding for your Garowe job for a written foreman allocation sheet: foreman name, site list, stage of each site and the deputy for absence. Take the sheet to the site and confirm the named person is present and knows the day's inspection points. Keep that sheet in the contract file and check it again at each stage, not only at the start.
Frequently asked questions
Can one foreman supervise two small Garowe sites in the same day?
Not continuously. He can visit both, but the pour, the setting out and the inspection all need someone present at the moment they happen, and a visiting foreman cannot be at two plots at once. Ask how the contractor covers the hours the foreman is away from your plot.
What should a client ask for to verify foreman capacity?
A written allocation sheet naming the foreman for the plot, a site list with stages and locations, the deputy arrangement, and contact details for two recent clients. Then walk the site and speak to the crew about who approves inspections.
Local reporting: this article is written for building work in Garowe and Puntland. Ground conditions, prices and rules differ between places; confirm the details for your own site.