In brief

  1. A snagging inspection only works when a named person has the authority and time to walk the finished work against a written list.
  2. Weak supervision leaves small defects such as sealant gaps, loose fixings and unsealed penetrations unrecorded until handover or the first rain.
  3. Request a room by room snag list with a sign off date before final payment, and confirm who checks the work in your contract.
Contents
  1. Where does site supervision fail at handover?
  2. What defects do missed inspections leave behind?
  3. How do you detect the gap before final payment?
  4. What to do next

Snagging inspections in Borama get missed when final supervision is treated as a formality rather than a walk through of the finished building. Someone has to check every room, roof edge, wet area and external joint against the drawings and the specification, write down what is wrong, and see it fixed. If the supervisor is already running a second site, or the client pays the last instalment before that walk happens, defects pass into the completed building unrecorded.

Where does site supervision fail at handover?

Supervision weakens at handover because the finishing trades arrive quickly and the checking time does not.

On many building jobs the supervisor carries a list of tasks across several plots. During structure the work is slow and visible. In the last weeks, tilers, painters, plumbers and electricians work in the same rooms at the same time. The supervisor signs off work they did not watch, because the labour force is ahead of the inspection. That is where the snagging gap opens.

A second gap is authority. If the site supervisor cannot reject work without the contractor's permission, defects get noted verbally and never written down. Ask the contract who has authority to stop a trade and who signs the completion certificate. Where a project has a clerk of works, project manager or client representative, that role should be in the contract documents, not agreed by phone.

A third gap is the punch list itself. A snagging list only works if it names the room, the item, the defect and the person responsible. "Touch up paint" is not a snag. "Bedroom 2, window reveal, crack in plaster, contractor" is one. This mechanism is the same on any site; ask the municipal engineer's office whether it holds any inspection checklist used for local buildings, and compare it with yours.

What defects do missed inspections leave behind?

Missed inspections leave behind small, repeatable defects that a short site walk would have caught.

In wet areas and on the roof, the items that show up later are sealant that does not bond to a dusty or damp surface, shower and floor falls that run the wrong way, and unsealed pipe penetrations through slab or wall. On windows and doors, they are gaps at the frame to wall junction, missing fixings, and thresholds that sit below the finished floor and let water in. On external walls, they are blown render, cold joints, and cracks at corners and openings.

Most of these defects do not fail on the day of handover. They fail in the first Gu or Deyr rain, or when the building is occupied and the room is full of furniture. Repair then costs more than the original work, because a finish has to be removed to reach the defect. Where a defect is structural, such as an unsupported block wall or a loose water tank base, it should be referred to the engineer before any cosmetic repair.

Ask the contractor for the test and inspection records for waterproofing, drainage falls, and electrical continuity. If those records do not exist, the snagging list is the only evidence of quality at handover. Walk a recently completed building in Borama and look at the same junctions, then write your own list of what you would have rejected.

How do you detect the gap before final payment?

The gap shows up when you compare what was signed off with what can be seen, so inspect before the final payment is released.

Set the inspection up as an event, not a favour. Give the contractor a written snag list with a date and a room by room format, walk the building yourself with the supervisor, and photograph each item. Ask for a joint inspection if your contract allows it. Check what your contract says about retention, defects liability and the final payment trigger before you agree to anything, and take advice if the terms are unclear.

Bring one person who understands the trades and one who does not. The second person finds the obvious things, such as a door that does not close or a floor that slopes. Check the roof and the water tank base yourself, and ask how the wet area falls were tested. Ask the plumber and electrician to demonstrate, not describe, their work.

For any structural item, ask the project engineer to confirm in writing before the repair is covered up. Keep a copy of the list and the photographs for the defects liability period, because the same junction may fail after the first rains.

What to do next

Write a room by room snag list today, name the person who signs it, and book the walk before the final payment is due. Ask the contractor for the inspection and test records that support the handover, and check your contract for the retention and defects liability terms. If the work is structural, ask the project engineer to inspect it in person.

Frequently asked questions

Who should carry out the snagging inspection in Borama?

The person named in the contract as responsible for completion checks, usually the site supervisor, clerk of works or project manager, walked with the client. The contract should say who has authority to reject work and sign the completion certificate.

When should snagging start on a building project?

Start as each trade finishes a room, not on the last day. Waiting until handover means finishes are already covered and defects such as wrong falls or unsealed penetrations cannot be seen without opening the work up.

What records should the client ask for at handover?

Ask for the snag list with dates and sign offs, photographs of repaired items, and test or inspection records for waterproofing, drainage falls and electrical continuity. If those records do not exist, keep your own photographs and list for the defects liability period.

Local reporting: this article is written for building work in Borama and Somaliland. Ground conditions, prices and rules differ between places; confirm the details for your own site.