In brief

  1. Work sequencing experience gaps show up when a team can build each trade but cannot order them so trades do not clash.
  2. Check a bidder's method statement, two week lookahead records and timesheets, not the number of years claimed.
  3. Agree the sequence in writing before mobilisation, with hold points the supervisor can sign off.
Contents
  1. How does the gap appear on a Burao site?
  2. How do you check work sequencing experience in Burao?
  3. What does the gap do to a project?
  4. What to do next

A work sequencing experience gap in Burao appears when a team can build each trade on its own but cannot order them so they do not clash. The result is concrete cut for a pipe laid later, plaster opened for conduit, or a slab cast before embedded items are fixed. The crew is not unskilled. The planning behind the work is thin.

How does the gap appear on a Burao site?

It appears as rework that nobody planned for: a finished floor opened for drainage, a block wall chased after painting, or a water tank base cast before the inlet position is fixed. A crew with sequencing experience sets the order of excavation, foundation, services, masonry, roof and finishes, and holds each trade until the item below it is signed off. When that order is missing, each gang works to its own programme and meets the others in the same place at the same time.

In Burao the climate can widen the gap. Hot, dry spells inland dry out fresh concrete and mortar, so a pour delayed by a clashing trade can be placed in worse conditions. Gu and Deyr rain can flood open excavations and trenches that should already be backfilled. Neither the heat nor the rain creates the clash. They make a clash that already exists more expensive.

You can check the local pattern without accusing anyone. Walk a recent building site with the supervisor and ask when the drainage and conduit went in relative to the slab and the floor screed. Ask the municipal engineer's office whether it holds approved drawings or inspection records for that plot.

How do you check work sequencing experience in Burao?

Ask for records, not years. A claim of ten years on site says nothing about whether the team can order trades. A two week lookahead, updated weekly, shows what the team expected to happen and in what order. Method statements for each trade show where the interfaces sit. Daily diaries and timesheets show whether the plan matched the work.

Ask a bidder to talk through one recent project from setting out to handover. Listen for the sequence and the hold points: when services were tested, when the roof went on, when wet areas were flood tested. A team that has done this will name the order without prompting. A team that has not will describe activities but not their dependencies.

The same check works for supervision. Ask who signs off each hold point and what happens when a trade arrives early. Confirm the answer against the project's specification and engineer, because the sequence and hold points belong in the approved method statement, not in general practice alone.

What does the gap do to a project?

It moves cost from the bid into the build. A low bid that assumes trades can overlap without a plan can win the job, then recover the difference through variations, extra labour or slower handover. The client sees a programme slip and does not see why, because each individual gang is working.

The second effect is quality. Services buried without inspection before backfill cannot be checked later without breaking the work. Rebar covered before the engineer inspects it cannot be verified from a photograph. Sequencing exists so that each item is seen and signed off while it is still open. That is general practice on building work; the specific hold points and inspection notice periods come from the project's specification and the engineer.

A third effect is dispute. When the order was never agreed, every clash becomes an argument about whose fault it was. Check what the contract allows for programme submission, revision and delay notices, and keep records that match the contract's requirements.

What to do next

Before mobilisation, put the sequence in writing. Ask the contractor for a method statement per trade, a two week lookahead and a list of hold points. Walk one recent site and compare the records with what was built. Agree who signs each hold point with the engineer, and check the contract for the notice periods that apply.

Frequently asked questions

What is a work sequencing experience gap?

It is when a team can carry out each trade but cannot plan the order in which trades meet, so work is opened, covered and reopened. It shows up as rework, not as poor workmanship in any single trade.

How do I check sequencing claims before I award a contract in Burao?

Ask for method statements, a two week lookahead and timesheets from a recent job, then walk that site and compare the records with what was built. Confirm the required hold points against the project's specification and engineer.

Does a low bid always mean weak sequencing?

No. A low bid can come from many causes. The check is the plan: if the bid has no sequence, no hold points and no lookahead, the programme carries the risk into the build.

Local reporting: this article is written for building work in Burao and Somaliland. Ground conditions, prices and rules differ between places; confirm the details for your own site.