In brief

  1. When no named person classifies defects, the person finishing the work decides what counts as a defect and how urgent it is.
  2. Repair urgency should come from the defect's effect on structure, water tightness and safety, not from how easy it is to fix.
  3. A supervisor can close the gap with one register, one inspection slot per trade and written confirmation from the designer.
Contents
  1. Who decides whether something is a defect?
  2. What does misjudged repair urgency cost?
  3. How do you detect the gap on a live site?
  4. What to do next

Defect classification supervision gaps in Qardho appear on any site where nobody owns the decision about what counts as a defect. Ask on site whether that is the case here. The mason, the carpenter, the electrician and the client each judge the work in front of them, and the smallest jobs get fixed first because they are easy. The structural and water-related defects wait, and they get worse.

Who decides whether something is a defect?

If the contract and the site diary do not name that person, the decision falls to whoever notices the item last.

General practice is for the supervisor or clerk of works to inspect each trade at defined stages and to record findings in writing. A defect register with a date, a location, a photograph and a short description gives the design office something to classify against. Without it, classification happens in conversation, and conversation favours the person who is present and talking.

Ask the project manager who signs off completed work before it is covered or closed. Then ask to see the last few signed records. If the answer is that the supervisor checks when he passes, the site has no classifier. Ask the relevant approving authority what records it holds for previous approvals on the plot, so you can see what was inspected in earlier phases.

What does misjudged repair urgency cost?

Urgency gets judged by how quickly an item can be finished, so cosmetic work jumps ahead of structural and water-related defects.

A crack in a column, a hollow patch under a floor slab and a missing damp course all take time to investigate, and none of them looks urgent on the day. A repainted wall looks urgent because it shows. When the register sorts by trade and date rather than by consequence, the cheap items close first and the expensive ones surface at handover, when access is harder and the finishes are already in.

Classification should sort by effect: does the defect reduce structural capacity, let water in, or create a safety risk? Those go first and stay open until the designer confirms the repair. Everything else can wait its turn. General practice is to re-inspect each repair and record the result, not to accept the contractor's word that it was done.

How do you detect the gap on a live site?

Walk the site and ask three people what they would do about the same defect, in front of the item itself.

If the answers differ, there is no classification system. Then check four things. First, whether the register exists and has entries from the last two weeks. Second, whether those entries name a location that can be found again. Third, whether any entry says who decided the repair method. Fourth, whether the last inspection was signed by someone other than the person doing the work.

A useful check is to pick one repaired item and trace it back through the register to the original inspection. If that trail breaks, classification is verbal. Request the test records for any concrete or fill that was placed and later repaired, and compare the dates. On a recent completed site, ask the client what was fixed after handover and how the decision was made.

What to do next

Set up one defect register this week with columns for date, location, photograph, trade, the designer's classification and the agreed repair. Give one named person the job of classifying every entry before repair starts. Walk the site with the designer and the relevant local authority to confirm the classifications against the current specification, and record the meeting.

Frequently asked questions

Who should classify defects on a Qardho building site?

General practice is for the designer or the supervising engineer to classify, with the supervisor recording the finding on site. The contract should name that person, so check the supervision clause before work starts.

How urgent should a water-related defect be treated?

Water entering the structure can corrode reinforcement and damage finishes over time, so it is normally treated as urgent and repaired before cosmetic items. Confirm the repair method with the designer before covering the work.

What records should a supervisor keep for each defect?

Date, location, a photograph, the trade involved, who classified it and which repair was agreed. That trail is what lets a client check later whether the repair actually happened.

Local reporting: this article is written for building work in Qardho and Puntland. Ground conditions, prices and rules differ between places; confirm the details for your own site.