In brief
- Handover competency is proven by records and a walk of the crew's last job, never by a CV clause that says maintenance was included.
- Ask who carried out the last service on each system and request the O and M manual, as-built drawings and commissioning records.
- Build a handover schedule into the contract so manuals, spare parts lists and training hours are deliverables with dates.
Contents
A client can only check maintenance handover competency in Qardho by asking one question: who actually operated and serviced the systems on the crew's last job? A claim that maintenance was included proves nothing. Ask for the operation and maintenance manual, as-built drawings, commissioning records and the name of the person who carried out the last service, then walk that site.
What does missing operating knowledge look like?
Missing operating knowledge shows up when the owner cannot answer basic questions about the installed systems. Nobody knows the pump duty point, the tank cleaning interval, the valve positions for isolating a leaking line, or which breaker feeds the borehole pump. Handover competency means the crew can sit with the owner and explain each system in plain terms, in Somali or English as the owner prefers. A competent handover covers how each item starts and stops, what normal running sounds and looks like, what to do when it trips, and which consumables and spare parts to keep. If the answers come only from the contractor's site agent and never from a named maintenance person, the knowledge has not transferred. Ask to see the training attendance list and the topics covered, and ask the owner to repeat one procedure back before the crew leaves site. The test is whether the owner can run the plant for a week without calling the contractor.
How do you verify maintenance handover competency claims?
Verification starts with records, not conversation. Ask for the operation and maintenance manual for each system, as-built drawings, test and commissioning sheets, a spare parts list with supplier names, and the maintenance schedule with intervals. Then ask who signed off the last service on a comparable job and arrange to visit it. On that site, speak to the person who now runs the equipment, not the contractor's staff. Ask how often the filters are cleaned, where the spare gaskets came from, and what failed first. A crew that genuinely handed over a plant can point to the manual they wrote, the labels they left on valves and panels, and the owner's own logbook. If the only evidence is a photograph of a completed building, treat the maintenance part of the claim as unverified and price the risk into the tender. Confirm any testing requirements with the project engineer or the municipal engineer's office before you rely on them.
How do you close the gap before you sign?
Make handover a set of deliverables with dates in the contract, not a promise at the end. The schedule can include the O and M manual for each system, as-built drawings, commissioning test records, a spare parts list with sources, labelled valves and panels, and a stated number of training hours for named owner staff. General practice is to tie the final payment to these items, so check what the contract allows and agree the wording with your engineer or lawyer before signature. During the works, ask the contractor to record the maintenance tasks carried out on site and who performed them. At the end, attend the training yourself and watch the owner's staff operate each system unaided. Where a system is critical, such as a pump set or a generator, ask the supplier to send its own technician for the handover session, and keep the signed sheet with the manuals.
What to do next
Before you sign or pay anything, ask the contractor for the O and M manual, the latest commissioning record and the name of the person who will train your staff. Then visit one completed job unannounced and ask the owner to run the plant. If those three items cannot be produced, hold the handover claim as unverified and ask the engineer to reprice or replace it.
Frequently asked questions
What documents should a maintenance handover include?
Ask for the operation and maintenance manual for each system, as-built drawings, commissioning and test records, a spare parts list with supplier names, labelled valves and panels, and a training attendance list. Confirm the exact list against your project specification or engineer.
How do I check a contractor's maintenance experience without a local reference?
Ask to visit a completed job and speak to the person who now runs the equipment, not the contractor's staff. Ask what failed first and where spare parts came from. If no visit is possible, treat the maintenance claim as unverified and price that risk in the tender.