In brief
- A site skills record pairs each worker's name with the tasks they have done under supervision, the evidence kept and the person who signed it off.
- The record works only if it is filled in on site, dated and tied to a specific element rather than written up at the end of the job.
- Ask the engineer or clerk of works to agree the record format before the first pour or the first block course.
Contents
A site skills record is a simple register that pairs each worker's name with the tasks they have done under supervision, the evidence kept and the person who signed it off. On a Puntland site it turns an informal crew into a tracked one, so a foreman can show which mason set which block course and who checked it.
What goes on a skills record?
Each line holds the worker's name, the task, the date, the element or grid reference, the name of the person who supervised the work and where the evidence sits. The evidence can be a site diary entry, a photo of the finished work or a signed checklist, whichever your contract or engineer accepts.
Build the record around the tasks the job actually contains: setting out, mixing, placing steel, block laying, formwork, curing and finishing. Ask the site engineer to list the tasks that need a named supervisor before work starts. Then add a column for the level of supervision, such as direct or periodic, and agree what that means on this site.
A record that names the task but not the supervisor tells you little. The value comes from the pairing: a named person accepts that a named worker did the work to the drawing and the specification. Our page on how to check a foreman's skills before hiring in Puntland shows what to ask before that person signs anything.
How do you fill it in without extra paperwork?
Fill it in at the same time as the site diary and the inspection request, not at the end of the month. One person, usually the foreman or clerk of works, keeps the register and updates it when a worker moves to a new task or element.
Keep entries short. A line such as "block course, ground floor, grid B2 to B4, laid by named mason, checked by named supervisor, photo 014" is enough. If a worker repeats the same task on the same element, one line covers the run with the dates.
Use the register when you plan the next stage. If no one has recorded placing steel under supervision, arrange it before the reinforcement is needed. Our construction risk analyzer lists workforce and quality risks with a reason and a mitigation, which can point to the gaps the record should close.
The register also feeds training decisions. Where several workers show no supervised entry for a task, plan a session on site with the engineer or a nominated tradesperson. The people and skills section collects the checks that go with this.
What do you do with it once it is running?
Review the register at each stage handover. Compare what the record shows with what the inspection and test plan requires, and list any task with no supervised entry. That list is the training plan for the next stage.
A register also helps when a worker leaves and a new one joins. The new worker's first entries show what they have done here, under whose supervision, and which tasks still need direct watching. Use the education page for learning paths that support the trades on site, and read how to check an apprenticeship is working in Puntland to link the register to trainee progress.
Where a worker claims a skill from another site, record it as a claim until it has been seen here. The first supervised entry settles it, and the record stays honest about what this crew has actually done.
What to do next
Draft one page with columns for name, task, date, element, supervisor and evidence location. Take it to the site engineer or clerk of works and ask whether the format meets the inspection and test plan. Start the register with the next element to begin and keep it beside the site diary.
Frequently asked questions
Does a skills record replace a trade certificate?
No. A certificate from a training provider records what a person studied. The site record shows what that person has done on this job under supervision, and the two together tell a foreman more than either alone.
Who should keep the register on a small Puntland site?
The foreman or clerk of works usually keeps it, because that person already signs the diary and inspection requests. Agree with the engineer who signs entries so the record carries weight at handover.